Our Orlando, Florida, branch was tasked with dewatering multiple areas to allow developers to raise a section of land that will be developed for a new subdivision.
The summary
The challenge
The solution
Holland Pump installed a 6″ hydraulic submersible system to support the transfer and placement of sand needed to raise the site for the building and parking areas.
To stabilise the ramp for heavy equipment, a wellpoint system paired with a 12″ rotary wellpoint pump was installed around its perimeter, keeping the sand dry and preventing washout or undermining. Once completed, the excavated area will serve as a pond and rainwater runoff basin.