Selwood supported George Leslie in delivering critical upgrade works at Glenkiln Reservoir on behalf of Scottish Water.
To enable installation of a new concrete cutoff and hydraulically operated scour valve, reservoir levels needed to be drawn down and tightly controlled between -1.25m and -0.175m below Top Water Level.
The existing 18” scour valve was unsuitable for prolonged level management due to silt disturbance and pollution risk, requiring a compliant temporary solution.