Siltbuster’s infrastructure water treatment specialists are supporting civil engineering joint venture EKFB with water treatment systems at its sites along the HS2 high-speed railway project. The customer is one of the four joint ventures, delivering around 80 km of infrastructure for the scheme.
So far, Siltbuster has supported with two-stage chemical treatment solutions at more than 60 EKFB sites, with systems ranging from 50 to 180 m3/h.
As part of a regular series of check-ups and meetings EKFB approached Siltbuster for several system upgrades in the G2S South and Central Sections of the route. Due to the progress of the work and the purchase of additional land, the main contractor needed bigger systems which meant upgrading the existing 50 m3/h to 120 m3/h systems with some locations being upgraded to 180 m3/h.