When Northumbrian Water needed to carry out essential maintenance to three pumps in a sewage treatment works (STW), Selwood were called in to assist. The feeder tanks required draining so that a survey could be carried out. This would allow for the teams to ensure Selwood’s replacement pumps were correctly positioned for the duration of the works.
Incoming flows at the STW average at 1400 l/s, so the tank drainage and survey would need to take place over night when the incoming flows are at their lowest. Selwood’s solutions team were tasked with draining down the feeder tank within 30 minutes, then carrying out a
laser scan within one further hour.