A Siltbuster Case Study

Automated CO2 pH Neutralisation & Clarification for Concrete Demolition Wastewater

Infrastructure

Sector

Pitlochry, Scotland, UK

Location

Discharge Point

Surface Watercourse

Flow Rate

10m3/hr

Effluent Type

Highly Alkaline Waters with Silty Suspended Solids

Global Infrastructure was tasked with demolishing concrete inside a generator house at Tummel Bridge Station, Pitlochry, to allow for refurbishment. The work generates water continuously, which needs to be collected and pumped to maintain a dry working area. The water mixing with the fine concrete particles results in an effluent with an elevated pH of around 11 and contains a significant suspended solids loading.