A Siltbuster Case Study

High-Flow Chemical Dosing & Clarification for Pipeline Flush Water

Water

Sector

Hemel Hempstead, UK

Location

Discharge Point

Surface Watercourse

Flow Rate

350m3/hr

The location of an existing Affinity pumping station and pipeline in Hemel Hempstead was within an area undergoing significant development. Chalk-based sediment from within the underlying aquifer had been mobilised as a result of drilling and piling works from adjacent construction sites. The mobilisation of sediment meant that the waters pumped, using the existing Affinity Water asset, were contaminated with slow-settling suspended solids. Normally on this site, clearance pumping was carried out and the washwater could be discharged directly to the adjacent watercourse.